Source page 1

Somerset
Rivers Authority

Annual Report
Summary
2021–22

Source page 2

Somerset’s 20 Year
Flood Action Plan and the SRA
The Somerset Levels & Moors Flood
Action Plan was published in March
2014, at the end of that winter’s
massive floods.
Those floods brought misery and
devastation to many, they closed 81
roads and cost Somerset an estimated
£148 million.

The Somerset Levels & Moors
Flood Action Plan

“We cannot let this happen again”

Prime Minister, David Cameron, 13th February 2014

Directly or indirectly, everybody in
Somerset was affected.
When Somerset Rivers Authority (SRA) was launched on 31 January 2015 the Flood Action Plan
was widened to include all of Somerset. The SRA oversees the Flood Action Plan. The Plan has six
main aims, stretching over 20 years, reflected in the workstreams in the following pages (W1 etc):
1.
2.
3.
4.

Reduce the frequency, depth and duration of flooding.
Maintain access for communities and business.
Increase resilience to flooding for families, agriculture, businesses, communities, and wildlife.
Make the most of the special characteristics of Somerset (with internationally important
biodiversity, environment and cultural heritage).
5. Ensure strategic road and rail connectivity, both within Somerset and through the county to the
South West peninsula.
6. Promote business confidence and growth.
All actions in the SRA’s annual Enhanced Programmes are scored against these objectives.
Activities in 2021-22
Somerset Rivers Authority is leading a revamp of Somerset’s 20 Year Flood Action Plan, working
with consultants WSP. The point of drawing up a Flood Action Plan in 2014 was to bring different
organisations and people together, so together they could do more. More to reduce local flood risks,
more to make local communities stronger, more to respond to local priorities in ways they could
not otherwise do.
Since 2014, a lot has been achieved. A lot has also changed. For example, dealing with climate
change is more of a priority for many people than it was eight years ago. Several SRA partners have
declared climate emergencies. More places have flooded. Next year a new Somerset Council starts.
The time is therefore right to discuss what needs doing next. In 2021-22 the SRA began consulting
partners and stakeholders about future local priorities. In autumn 2022, people across Somerset
will be asked for their views about what should be done to give Somerset more protection from
flooding and greater resilience. A revamped plan will be approved by the SRA Board and published
in March 2023.

2

Source page 3

W1

DREDGING & RIVER MANAGEMENT

Baldr and Havik working in combination
DREDGING
Maintenance dredging in January 2022 covered 3.75km (2.33miles) of the River Parrett between
Saltmoor Pumping Station and Andersea. It was organised for Somerset Rivers Authority (SRA) by
the Parrett Internal Drainage Board (IDB), working as a partner in the SRA. The Parrett IDB liaised
closely with the Environment Agency and Natural England, and again deployed water injection
dredging specialists Van Oord. They used dredging unit Baldr and tug boat Havik (above).

RIVER SOWY-KING’S SEDGEMOOR DRAIN ENHANCEMENTS
0.82 miles of bank raising, seven new ecological features, delivered for the SRA by the
Environment Agency as part of a scheme to help reduce flood risks across 150 square miles.
OTHER PROJECTS
Silt monitoring to help target dredging. River Brue modelling commissioned. Strategic
Approach to Mitigation progress, including a third round of winter habitat and bird surveys.
Structures desilted in Bridgwater, Cheddar, East Stoke and Perry Street. Sampford Brett
works finished. Dulverton Weir survey and design work carried out. The SRA part-funded several
schemes led by other bodies, with which: the Government formally approved the building of a
Bridgwater Tidal Barrier; a big Taunton flood alleviation scheme progressed; two planning
applications for river restoration on the National Trust’s Holnicote estate were made to the
Exmoor National Park Authority. Langport flow station building now due 2022.
For more information, see the full-length Annual Report or visit the SRA website.

3

Source page 4

W2

LAND MANAGEMENT INCLUDING

NATURAL FLOOD MANAGEMENT (NFM)

The SRA funds many Natural Flood Management (NFM) activities across Somerset. All sorts of
different techniques may be used, singly or in combination. All share the aim of reducing local flood
risks, by slowing the flow of water down through catchments in ways that work with nature.

Scrape with timber

Scrape with timber

Nine schemes constructed in 2021-22 included a series of floodplain restoration works in
Witham Friary (pictured above) along Hermitage Stream, which is a tributary of the River Frome.
OTHER PROJECTS
12 highway referrals seeking answers to
road flooding problems in better management
of land nearby, 1 soil visit to help reduce the
run-off of surface water. NFM activities like
planting cover crops (as at Stawell, top) at 27
farms winning online auction grants and 4
Doniford catchment farms in West Somerset.
Volunteers planted Trees for Water at 39
places, such as Windsor Hill (right).
For more information, see the full-length
Annual Report or visit the SRA website.

4

Source page 5

W3

URBAN WATER MANAGEMENT

Stoke St Gregory detention basin

Monkton Heathfield

The main aims of Somerset Rivers Authority’s Urban Water Management workstream (W3) are to
reduce local flood risks and make places better to live and work. A lot of close attention is devoted
to examining Sustainable Drainage Systems (SuDS) at new developments.
When it rains, SuDS help to control the run-off of water from hard surfaces like roads, roofs and
pavements. SuDS use techniques inspired by nature – such as permeable paving and plants and
ponds – to absorb water and hold it back. SuDS can make places greener and more attractive,
healthier for people and better for wildlife, with less pollution.
Very few formal SuDS inspection processes are in place across England: Somerset is ahead in
checking new developments. The SRA funded inspections of SuDS at 41 places in 2021-22,
including Bridgwater, Burnham-on-Sea, Chard, Langport, Monkton Heathfield, Shepton Mallet,
Taunton and Wellington. Inspectors check schemes for compliance against 16 different criteria.
The SRA and its partners want to ensure that SuDS are built in accordance with the exact designs
that were approved by local planning authorities, and that they work as they are meant to work.
Local planning authorities have the power to enforce changes to constructed SuDS schemes, and
where necessary they use this power.
Croscombe

OTHER PROJECTS
Activities in Rode included computer model
development to enable drain and watercourse
capacity-testing, and installing a field drain.
An ongoing study of the catchments of
Croscombe, Shepton Mallet, and places in
between such as Bowlish, saw several surveys
done along with some vegetation clearance
and jetting. In Minehead, a 2D Integrated
Catchment Model is being developed to get
a better understanding of local surface water
flood risks.
For more information, see the full-length
Annual Report or visit the SRA website.

5

Source page 6

W4

RESILIENT INFRASTRUCTURE

Two of the six main objectives in Somerset’s 20 Year Flood
Action Plan are about making Somerset’s infrastructure more
resilient. They urge that access should be maintained for people
and businesses travelling within Somerset or through the county.
As it oversees the Flood Action Plan, Somerset Rivers Authority
therefore deals with highways as well as waterways.
IMPROVEMENTS THROUGH CARHAMPTON
For many years the A39 at Carhampton Cross regularly flooded
so badly it was dangerous or impossible to drive through. As the
A39 is the main road serving West Somerset, widespread
disruption resulted for residents, businesses and visitors.
Problems were made worse by water cascading down from
Carhampton Cross, regularly flooding the B3191 Eastbury Road,
and hitting people’s homes. Drainage systems were simply
overwhelmed by the amount of water pouring off land nearby.
The SRA therefore teamed up with Somerset County Council’s
Highways Department for a pleasingly successful series of major
drainage upgrades.
SRA-funded improvements along the A39, B3191 and nearby Hill
Lane included bigger pipes, better gullies, and new water control
features such as concrete chambers and a catch-pit. Somerset
County Council paid for extensive road resurfacing.

A39 Carhampton
B3191 Carhampton

OTHER PROJECTS IN 2021-22
The SRA funded extra maintenance for 13,622 gullies, 125
drains, 8 trash screens, 56 silt traps to help keep roads open,
make them safer, preserve access for communities and safeguard
properties from flooding.
Extensive drainage improvements were made in the Lodes
Lane area of Kingston St Mary on the edge of the Quantocks near
Taunton, and in the Urgushay Road area of West Camel in South
Somerset. Individual drainage features were upgraded
in Bruton, Castle Cary and Cucklington in South Somerset,
Chilcompton and Ditcheat in Mendip, and Mark in Sedgemoor.
An unstable section of bank was stabilised in Chadmead
(Sedgemoor). An SRA-funded study of the Mill Stream
catchment around Rimpton and Marston Magna in South
Somerset suggested eight options for improvements, such as desilting, infrastructure replacement and installation, and creating
flood water storage features.
For more information, see the full-length Annual Report or visit
the SRA website.

6

West Camel

Source page 7

W5

BUILDING LOCAL RESILIENCE

Robin Huish, Ham Village Flood Defence Committee

Being mostly about people, this workstream was affected during 2021-22 by Covid-19 concerns
and restrictions. In autumn 2021, Somerset’s annual Community Resilience event (part-funded
by the SRA) largely consisted of online training sessions. However, come spring, there were 10
public screenings of SRA-commissioned film Down by the River, which celebrates local volunteers
(including the trio on the top half of this page). The film is now on YouTube. The SRA’s community
engagement team supported residents in places recently affected by flooding, including Chard,
Combe St Nicholas, Forton and Tatworth, Ilminster, Shepton Mallet and Croscombe, and they
worked with volunteers in Ruishton and Ham, Burrowbridge, North Petherton, Martock and
Langport. They visited two schools, gave talks to Long Sutton Gardening Club and Langport
Rotary Club, and took part in SCOP26+, Somerset’s version of the global event held in Glasgow.

Teresa Bridgeman

Gordon Swindells
OTHER PROJECTS IN 2021-22
Grants for equipment were given to flood
warden teams in Ham, Croscombe and Martock.
The SRA part-funded Adapting the Levels, a
major project about the water-related effects
of climate change (flooding and drought).
Recent developments include mobile app
Somerset Trails featuring Wedmore and a
Kids Corner with Iona (left), an online tool for
exploring adaptation pathways, new Moor
Associations and new proposals for water
storage and peat.
For more information, see the full-length
Annual Report or visit the SRA website.

7

Source page 8

Financial Summary
The SRA gets annual funding from two sources. Firstly, council tax: Somerset’s local authorities
raise money for the SRA. Secondly, the Parrett and Axe Brue IDBs each give £10,000. In 2021-22,
from these two sources, the SRA received Local Partner Funds totalling £2,941,586.
In March 2021, the SRA Board topped up that total with funds moved out of contingency. They set
a budget of £3,440,000 to cover the SRA’s 2021-22 Enhanced Programme of works. Further funds,
also carried forward from the previous year, were allocated to four full-time staff, a new parttime Technical Adviser post, administration and overheads. The 2021-22 Enhanced Programme
contained 21 schemes and activities, all designed to advance Somerset’s 20 Year Flood Action Plan.

Spending of Local Partner Funds in 2021-22
Many actions and initiatives are completed within one financial year. Some require longer-term
research, design, planning and implementation. In 2021-22, coronavirus pandemic restrictions
continued to affect delivery, so less was spent than originally expected. The table below shows all
of the Local Partner Funds held by the SRA at the beginning of the 2021-22 financial year and the
SRA’s total spend during the year. Remaining funds are carried forward into future years. For
more information, see the full-length Annual Report or visit the SRA website.
2021-22 SPENDING
BY WORKSTREAM

TOTAL £

%

Dredging and River Management
Land Management
Urban Water Management
Resilient Infrastructure
Building Local Resilience

1,377,000
498,000
193,000
408,000
121,000

48.6
17.6
6.8
14.4
4.3

SUB TOTAL

2,597,000

Staffing, administration, overheads
SRA Development Activities

214,000
20,000

TOTAL

2,831,000

LOCAL PARTNER FUNDING
2021-22 FINANCIAL
SUMMARY

7.6
0.7

ALLOCATED
FUNDS AT START
OF 2021-22
FINANCIAL YEAR
£

SPEND IN
2021-22
£

ALLOCATED
FUNDS
CARRIED
FORWARD
TO 2022-23
ONWARDS
£

10,388,000

2,831,000

7,557,000

TOTAL
Copyright © 2022 Somerset Rivers Authority

8

TOTAL
£2,831,000

www.somersetriversauthority.org.uk
www.twitter.com/SRAnews
www.facebook.com/SomersetRiversAuthority